To achieve the results you are asking about, you will need to do the following:

1) Create a Zip Codes Table where each record is a Zip Code that will be assigned to your projects.
2) In the Zip Codes table, designate a Zip Code (text) field as the key field. (Normally Record ID#)

February 5th, 2009 - 6:02 PM

Create two summary fields in the Projects table. The first summary field will be labled "Number of Tasks". It should be configured to count the number of Tasks. The second summary field should be labeled "Number of Completed Tasks". It should be configured to also count the number of related Tasks with a condition to include only the Task records where the "Status" field is "Completed".

February 5th, 2009 - 6:02 PM